Gents,
If you have been following my build, it started out in my garage, and I moved it to my basement. I have posted some pics as we have progressed.
The trusses come out tomorrow, followed by eight 4 X 4 1/4 steel tubes that will run along each side of the top 2X4 of the joist to support the ceiling above. This is giving me a swing height of 8'11 inches. That's all I could get without digging down. It was hard cutting that check for $9k, but it had to be done.
My GCQuad will be delivered next week.
The electrical and HVAC has all been moved. Screen has come down as has the putting green floor so they don't get destroyed by sawdust. Gasline has been rerouted underneath the joists.
Last weekend, in between trips out to Quail for the Wells, I ran my HDMI cord from the wall where my gaming PC will go inside of a cabinet, to an opening where my projector will be placed once drywall goes up. Also ran a Cat6 from my router, through the wall, and to my PC
2 questions for you all.
What am I missing as far as cords that need to be installed/routed before drywall?
I know I will still need some lighting solution above my hitting mat, any suggestions?
Any suggestions on a computer cabinet?
If you have been following my build, it started out in my garage, and I moved it to my basement. I have posted some pics as we have progressed.
The trusses come out tomorrow, followed by eight 4 X 4 1/4 steel tubes that will run along each side of the top 2X4 of the joist to support the ceiling above. This is giving me a swing height of 8'11 inches. That's all I could get without digging down. It was hard cutting that check for $9k, but it had to be done.
My GCQuad will be delivered next week.
The electrical and HVAC has all been moved. Screen has come down as has the putting green floor so they don't get destroyed by sawdust. Gasline has been rerouted underneath the joists.
Last weekend, in between trips out to Quail for the Wells, I ran my HDMI cord from the wall where my gaming PC will go inside of a cabinet, to an opening where my projector will be placed once drywall goes up. Also ran a Cat6 from my router, through the wall, and to my PC
2 questions for you all.
What am I missing as far as cords that need to be installed/routed before drywall?
I know I will still need some lighting solution above my hitting mat, any suggestions?
Any suggestions on a computer cabinet?