    My Man Cave Golf Simulator Build

    Finally, I upgraded from the NetReturn and building the whole basement into golf simulator with putting green/semi home theater. It took 6 months to get all the parts, and I was lazy to work on it. Here is my room size and I'll list the items I bought for this project and post a few progress pictures later tonight.

    Room size 15'x22'x9'
  • bongta029
    Senior Member
    • Nov 2016
    • 106

    #2
    Originally posted by bongta029 View Post
    Finally, I upgraded from the NetReturn and building the whole basement into golf simulator with putting green/semi home theater. It took 6 months to get all the parts, and I was lazy to work on it. Here is my room size and I'll list the items I bought for this project and post a few progress pictures later tonight.

    Room size 15'x22'x9'
    What I had for my first build
    Skytrak
    Netreturn Pro Series (sold)
    6'x10' Residential Golf Mat (sold)

    What I bought for upgrading sim
    1'x3' Fiberbuilt fairway panels
    15'x22' Putting Elite Green Turf Factory Direct.
    13'x8.5'x5'Carl's Premium custom enclosure kit
    1"Dricore R Panels
    Optoma uhd51alv 4k projector
    Nvidia RTX2070 graphic card

    I used the new screen on the carpet with 6'x10' mat fir the past few months, and this week I'm installing the green.

    This is how much I got it done yesterday. I can't wait to complete it by tomorrow.

    Comment

    • Gman17
      Senior Member
      • May 2019
      • 133

      #3
      Looking good!! 6 months for the parts and 1 week to build, if not sooner!

      Comment

      • phoneman68
        Junior Member
        • Jun 2019
        • 12

        #4
        Looks good

        Comment

        • bongta029
          Senior Member
          • Nov 2016
          • 106

          #5
          I spent 2 hours last night to remove the rest of the carpet and rack strips. And I spent 3 hours today so far to install rest of the dricore panels. Now it's time for the putting green!

          Comment

          • Trainor
            Junior Member
            • Jun 2019
            • 22

            #6
            Watching this. Great work. Starting my build this week

            Comment

            • bongta029
              Senior Member
              • Nov 2016
              • 106

              #7
              90% complete.
              Installed the putting green in the afternoon. It was hard to align them. I ended up making a wrinkle because I folded it to move my screens back and forth. Damn it. Does anyone know how to remove it?
              Now I need to trim the edges amd cut the hole for the panel.

              Comment

              • bongta029
                Senior Member
                • Nov 2016
                • 106

                #8
                It is done! Cleaned for another 2.5hrs.
                It took me 15hrs since last Thursday, but I'm so glad it's complete. Now I can enjoy beer and start playing again tomorrow.

                Comment

                • gene438
                  Super Member
                  • Jan 2016
                  • 703

                  #9
                  Outstanding work....I predict many, many years of enjoyments. Congrats....it looks great.

                  Comment

                  • Gman17
                    Senior Member
                    • May 2019
                    • 133

                    #10
                    Nice job! I ordered my lumber today and it will be delivered on Wednesday. I can't wait to start sawing. How did you do your FB cut out? Trim a little at a time until you were flush?

                    Comment

                    • bongta029
                      Senior Member
                      • Nov 2016
                      • 106

                      #11
                      Thanks. I will be playing and pratice a lot more often now.

                      For the FB panel, I did cut it with scissors. Started from far side away from standing side and worked around it. 2 sides where the ball rolls and you see when you stand were straight and flush, but the other sides were slightly were off here and there by 1/4". Ball rolls pretty well for putting from the fb panel.

                      Comment

                      • MadeInBrooklyn
                        Member
                        • Mar 2019
                        • 37

                        #12
                        Awesome looking build! My build is almost complete just waiting on my screen to put it all together and ill post some pics, its very similar to the products you have. I got a Carl's premium also, how do you like it so far?

                        Comment

                        • EasyW
                          Member
                          • May 2019
                          • 52

                          #13
                          Well done. Very clean and super fast build. Your planning really made a difference. Enjoy!

                          Comment

                          • JD0526
                            Member
                            • Nov 2018
                            • 35

                            #14
                            Awesome work , I’m jealous. Wish I had a dedicated area that large

                            Comment

                            • WPStangs
                              Member
                              • Apr 2017
                              • 30

                              #15
                              Looks great!